The following overview represents a summary of the key milestones achieved in the general development of the company:

  2010
   
April CGS provides Fluor Limited Notice to Proceed
   
March The German authorities have granted the Rahmenbetriebsplan Permit for our Phase 1 developments in Epe.
   
January CGS has appointed ILF as the Lender's Engineer
   
 

2009

   

November

Tender for EPC

   

November

Public hearing for Rahmenbetriebsplan (Frame Operating Plan) permit

   

July

Submission of Rahmenbetriebsplan (Frame Operating Plan)

   

June

RBS engaged as Equity Advisor (private placement)

   

June

Commissioned Fluor Engineers of The Netherlands to review FEED (Front End Engineering and Design) and study and quantify EPC

   

June

Completed FEED (Basic Engineering) of phase 1

   

February

Application made to E.ON/RWE (regional gas network operators in Germany) for grid connection

   

January - February

CGS management met with the German energy market regulator in Bonn and its EU counterpart in Brussels, to address any competition matters and compliance with current German and EU regulatory frameworks. CGS’ Epe project was received positively by both regulators.

   

January

Scoping document of the application for Rahmenbetriebsplan (Frame Operating Plan) submitted to Bezirkregierung Arnsberg. This permit is the necessary to enable the project to be financially closed.

   

 

2008

   

November

Landschaft und Siedlung (LUS) of Recklinghausen, Germany, has been retained to oversee the environmental data collection and analysis of the environmental impact study and reporting work.

   

November

Private placement closed with large bank

   

November

Cavern Option Agreement notarized and closed with Salzgewinnungsgesellschaft Westfalen (SGW)

   

November

Capacity Option Agreement signed and closed with trading arm of large bank

   

October

Surface Rights Land Options agreed with landowner for phase 1 facility

   

October

Capacity option agreements signed with 34 Stadtwerke

   

July

Seed round financing closed

   

June

Consultant firm of Germany retained to assist with local land acquisition and development work

   

March

Signed reservation agreement with a large global commodities trading group

   

February

Began seed round investment

   

 

2007

   

November

Signed SGW cavern reservation agreement

   

August

Continental Gas Storage BV incorporated as Dutch private limited liability company

 

Last update: 14 April 2010